ENQUIRY ON CONTROL MECHANISMS DEPLOYED BY THE MALTA TRANSPORT AUTHORITY (ADT) IN ROAD CONSTRUCTION PROJECTS PARTLY FINANCED THROUGH THE FIFTH ITALO-MALTESE FINANCIAL PROTOCOL
The Auditor General reported to Parliament on an enquiry requested by the Public Accounts Committee on control mechanisms deployed by ADT in managing variations in the road construction projects partly financed through the Vth Italo-Maltese Financial Protocol.
The enquiry consisted of an evaluation of these control mechanisms and an outsourced technical expert evaluation of the relevant tender and supporting documents.
Whilst noting the timely completion of the projects, and a marked improvement in the planning process, the following main shortcomings were noted:
- Treating the projects as a departmental tender resulted in safeguards afforded by the Public Procurement Regulations being replaced by new, untested systems.
- Ministry of Finance approval for ADT to manage the projects outside the most commonly applied provisions in the public sector procurement regulatory framework did not take into account extra-budgeted expenditure. From an originally-allocated Lm12.9M (Italo-Maltese Financial Protocol funds dedicated to road works), project expenditure totalled Lm16.5M.
- ADT delegated project management responsibility to (external) Supervisors who had been nominated by the Contractors. No evidence was found to prove that ADT abided by Ministry of Urban Development and Roads instructions to maintain its own controls.
- NAO checks on a sample project revealed that ADT had adopted an unorthodox payment process whereby the Contractor account was at times in credit.
- Errors were encountered in bills. These had gone undetected for some time before being adjusted and in one instance the error went unnoticed.
- Issues arise with the manner with which ADT adopted a modified version of the FIDIC model of contract, with all the implications of such modifications.
- The role of the Supervisor was not correctly defined and the perception of transparence, effectiveness and accountability was clouded by the perceived link between Contractor and Supervisor. The various roles assigned to the Supervisor within the contract blurred this separation further.
A number of recommendations to address these issues were made.
The report can be found on NAO Website: www.nao.gov.mt with effect from 16 June 2009.
DOI – 15.06.2009