RECONSTRUCTION OF ROADS IN LOTS 2 AND 3 FUNDED UNDER THE FIFTH ITALO-MALTESE FINANCIAL PROTOCOL STARTS

PR1024
Date Icon 18/06/2004

Work on the reconstruction of the second and third lots of arterial and distributor roads funded under the 5th  Italo-Maltese Financial Protocol started earlier this week with the scarifying of two parts of Żebbuġ Road which leads from Rabat to Qormi. The work forms part of a Lm12.5 million project which is due for completion in November 2005.

Italian Contractor F.lli Basillotta Srl has been entrusted with the reconstruction of the section of road from the junction near the Mtarfa Cemetery down to the Siġġiewi Road junction in Żebbuġ.

Work on Phase 1 of Lot 2 involves the reconstruction of both carriageways of Żebbuġ Road (Route 21) from the Saqqajja roundabout to the Żebbuġ road junction. The stretch of road is 2.2 kilometres long. Southbound traffic from Rabat to Żebbug is being diverted through Mdina Road (Route 7) and Żebbuġ Road (Route 25). Work on the other carriageway is expected to start next week when northbound traffic will be diverted through Routes 7 & 25 as well.

The work involves the complete reconstruction of the road surface, kerbs and construction of a service duct. This stretch of road is expected to be delivered by September this year.

Meanwhile work is also proceeding at a steady pace on the northbound carriageway of an 800-metre stretch of Żebbuġ Road (between the Siġġiewi Road junction and Triq Angelo Borg junction in Qormi) which forms part of Lot 3.

The first phase of this project entails the reconstruction of the road surface and kerbs, construction of a service duct and the shifting of all utilities including electricity, water, telephone and cable television.

Northbound traffic is being diverted on the southbound carriageway which has been temporarily converted to accommodate two-way traffic.

This phase of the project entrusted to Italian contractor F.lli Anastasi Snc and Maltese subcontractors Asfaltar Co. Ltd. will be delivered by mid-September when work on the southbound carriageway is expected to start.

The reconstruction of the remaining part of Lot 3  comprising Qormi Road from Qormi to the junction near the Airport’s cargo terminal is expected to start before the end of summer.

Share this Press Release Icon socials Icon socials Icon socials Icon socials

Other Press Releases:

STQARRIJA MILL-MINISTERU GĦAL GĦAWDEX  ŻiguŻajg jirritorna Għawdex għat-tielet darba bil-produzzjoni ‘What’s Missing’ għall-istudenti

PR261939

STQARRIJA MILL-MINISTERU GĦAL GĦAWDEX ŻiguŻajg jirritorna Għawdex għat-tie...

PRESS RELEASE BY THE MINISTRY FOR EQUALITY AND CIVIL RIGHTS Malta records one of the strongest improvements in gender equality in the EU

PR261938en

PRESS RELEASE BY THE MINISTRY FOR EQUALITY AND CIVIL RIGHTS Malta records o...

More Press Releases Right arrow