ROAD NETWORK UPGRADE WORKS FUNDED UNDER THE FIFTH ITALO-MALTESE FINANCIAL PROTOCOL - THE ROAD SO FAR

PR0725
Date Icon 19/05/2005

The Ministry for Urban Development and Roads through the Network Infrastructure Directorate within the Malta Transport Authority is heavily involved in overseeing the successful execution of Malta ’s most ambitious road upgrade programme covering a total of 16-kilometre corridor of arterial and distributor roads in the centre of the island.

These works, worth €30 million are being funded under the Fifth Italo-Maltese Financial Protocol and involve the complete reconstruction of these roads, realignment and shifting of utility infrastructures through common service ducts. The roads are being built to a projected lifespan of 25 years. Work on the Fifth Italian Protocol road upgrade programme started in June 2004 and is due to be completed by September 2005.

Three contracts were awarded to three Italian contractors in June 2004 for road upgrade works on 12km of roads leading from Luqa to Tarġa Gap in Mosta via Qormi, Żebbuġ, Ta’ Srina and Tal-Qlejja. These works were divided into three lots, each going to a different contractor. Lot 1 was awarded to Ergon Engineering and Maltese sub-contractor Polidano Bros, Lot 2 went to F.lli Basilotta while Lot 3 was awarded to Italian firm Anastasi Snc and Asfaltar Co. Ltd as their Maltese sub-contractors. The contractors mobilised on site between the 8th and 10th of June 2004.

A further three contracts were awarded to another three Italian contractors in November 2004 for the reconstruction of an additional 4 kilometres of roads, bringing the total length of roads being redone with funds from the Fifth Italo-Maltese Protocol to 16km – more than 10% of the arterial and distributor road network of Malta.

The Italian contractors brought in at this stage were Societa` Internazionale Gallerie srl, Integra srl and Mattioli spa. These were amongst six contractors that had originally submitted bids for Italian Protocol road works. They were awarded these contracts after they revised downwards the prices they quoted in their original bids by a considerable degree.

All three Italian contractors are engaging Maltese sub-contractors to carry out these works. Societa` Internazionale Gallerie srl has engaged Polidano Bros. Ltd as its subcontractor, Integra srl has engaged Bonnici Bros. and General Road Services while Mattioli spa has Bitmac and Tal-Ġeneral as its subcontractors. The mobilisation for these three contracts took place during January this year.

Thus, the road works funded under the Fifth Italian Protocol are being distributed over a larger number of contractors, hence ensuring that the works are finished in the shortest time possible. This will also ensure that more Maltese contractors benefit from the technology transfer that close collaboration between Maltese and foreign road contractors brings with it.

Though the original term of the Fifth Italo-Maltese Protocol has been extended by two years till September 2007, the programme of works on these roads has not changed and the deadline for their completion remains September 2005.

Work on several road stretches is now nearing completion and delivery. One particular stretch – 1.4 km long in Qormi – has already been delivered and is now open to traffic. A second stretch of Mdina Road between Żebbuġ and Rabat – 2.2 kilometres long – will be opened to traffic this weekend.

Share this Press Release Icon socials Icon socials Icon socials Icon socials

Other Press Releases:

STQARRIJA MILL-UFFIĊĊJU TAD-DEPUTAT PRIM MINISTRU U MINISTERU GĦAS-SAĦĦA  Ċertifikazzjoni internazzjonali tal-ogħla livell għad-dipartiment tar-radjoterapija fiċ-Ċentru tal-Onkoloġija Sir Anthony Mamo

PR261947

STQARRIJA MILL-UFFIĊĊJU TAD-DEPUTAT PRIM MINISTRU U MINISTERU GĦAS-SAĦĦA Ċ...

STQARRIJA MILL-MINISTERU GĦALL-EDUKAZZJONI U L-ISPORT  Aktar minn 1,800 student jiggradwaw mill-Università ta’ Malta

PR261946

STQARRIJA MILL-MINISTERU GĦALL-EDUKAZZJONI U L-ISPORT Aktar minn 1,800 stu...

More Press Releases Right arrow