MORE ROADS INCLUDED IN PROGRAMME OF WORKS FUNDED UNDER 5TH ITALO-MALTESE FINANCIAL PROTOCOL
Minister for Urban Development and Roads, the Hon. Jesmond Mugliett, this morning presented letters of acceptance to three Italian road contractor that will carry out reconstruction works on three primary roads in the centre of Malta . This work is being funded under the 5th Italo-Maltese Financial Protocol.
The letters of acceptance of these three roads were presented to Societa` Internazionale Gallerie srl, Integra srl and Mattioli spa. These were amongst six contractors that had originally submitted bids for Italian Protocol road works. They are being awarded these works after they revised downwards the prices they quoted in their original bids by a considerable degree.
All three Italian contractors are engaging Maltese sub-contractors to execute these works.
· Societa` Internazionale Gallerie srl has engaged Polidano Bros. Ltd as its subcontractor,
· Integra srl has engaged Bonnici Bros and General Road Services while
· Mattioli spa has Bitmac and Tal-Ġeneral as its subcontractors.
Thus, the road works funded by the Italian Protocol are being distributed between a larger number of contractors, hence ensuring that the works are finished in the shortest time possible. This will also ensure that more Maltese contractors benefit from the technology transfer that close collaboration between Maltese and foreign road contractors brings with it.
The roads that will undergo reconstruction are the road between the roundabout junction near St. Dorothy’s School in Żebbuġ and De Rohan Gate, the road that leads from Tal-Qlejja l/o Mosta and Żebbiegħ and the road that leads from Żebbuġ to Siġġiewi.
Minister Mugliett said that the 2.5 kilometre stretch from Tal-Qlejja to Żebbiegħ and the 1.5 kilometre-long Siġġiewi Road are being included in the programme of works at this stage because Government had retained Lm2 million from the Italian Protocol so as to ensure that the works awarded previously did not exceed the Lm12.5 million available under the terms of the Protocol.
With the inclusion of these two roads, the total length of roads that will be reconstructed with funds from the Italian Protocol will increase from 12 to 16 kilometres.
“Six months after the start of the project, we can assess the situation more clearly. Since the estimates are generally in line with the real value of the works, the Lm2 million that we were holding back can be awarded as additional works,” said Minister Mugliett.
The road between the roundabout junction near St. Dorothy’s School in Żebbuġ and De Rohan Gate already formed part of the works that were awarded to an Italian Contractor in May. This contractor, however, was falling back on the schedule of works that he had submitted. Following negotiations, this contractor agreed to give up some of the works he had been awarded so that these can be given to another contractor, on condition that he will be awarded further works if he catches up.
Meanwhile, the work on the first phases of the three lots of road works that were awarded in May is proceeding steadily and the first layer of tarmac is being laid on parts of them. Some of these will even be opened to traffic in the coming few weeks.
Minister Mugliett said that all the roads that are being funded under the Italian Protocol are introducing new practices in road construction – practices such as the use of pre-cast common service ducts, the integration of stormwater culverts in the design of the roads, the importation of aggregate for use in the wearing course as well as the monitoring and quality assurance that are being carried out at every stage.
“Thanks to these practices, the Maltese public will be able to use these works for thirty years before these will need to be resurfaced,” said Minister Mugliett.
He added that now that the first phases of these works are nearing their completion and the contractors are getting used to these new practices, work on the rest of the Italian Protocol Works is expected to speed up.
The Minister for Urban Development and Roads said that though the Fifth Italo-Maltese Protocol has been extended by two years, the programme of works on these roads has not changed and the deadline for their completion remains October 2005. The Minister concluded by saying that this is an important factor in light of the works that will be funded by the European Union, which will have already started by that time.
DOI - 23.11.2004
10.33 Kbytes Last Modified on 23rd November, 2004
HOME | GOV.MT
HELP | LINKS | SITEMAP | SEARCH
Other Press Releases:
PR261947
STQARRIJA MILL-UFFIĊĊJU TAD-DEPUTAT PRIM MINISTRU U MINISTERU GĦAS-SAĦĦA Ċ...
PR261946