PERFORMANCE AUDIT: HOUSING AUTHORITY’S PROCUREMENT OF REPAIR WORKS ON RESIDENTIAL UNITS
In view of the significant social implications that social housing entail, the National Audit Office (NAO) has conducted a Performance Audit to assess whether the Housing Authority (HA) carries out its responsibilities relating to the procurement of repair works on residential units in a manner which maximises efficiency, effectiveness and economy considerations. Although such repair works are acquired through a number of different procurement methods, this study was scoped to cover works acquired through call for quotations and direct orders during the year 2013.
Although NAO noted a number of good practices employed by the HA, some concerns on its modus operandi have also emerged. Most notably, this Office observed that significant weaknesses were identified in the manner by which the Authority maintains its databases listing complaints lodged by residing tenants. NAO’s concern was further compounded when it observed that the Authority does not keep a comprehensive compilation of all the residential units under its responsibility, making the task of identifying whether a residential unit falls under its responsibility or otherwise considerably more onerous.
This Office also identified a number of concerns on the manner by which the Authority engages in the reviewed procurement processes. Of the more salient findings, NAO noted that, as at end 2013, HA had approximately 700 pending requests for works to be carried out and, in an attempt to address this backlog, the Authority drafted a Framework Agreement so that it could start commissioning works to address this accumulation by direct orders, each not exceeding €6,000 (excluding VAT) in value. While this Office acknowledges the urgency of such a situation, it is nonetheless concerned about the fact that, by utilising such a procurement system, a considerable number of interventions are being awarded to selected contractors without the introduction of a competitive element, thereby forfeiting potential savings. NAO is also concerned on the manner by which the fixed prices quoted in these contracts were determined by the Authority as, rather than carrying out a study to establish fair and reasonable prices, HA based its rates on past bids submitted by contractors, subjecting itself to the risk of quoting inflated market prices.
In an Expression of Interest, where contractors wishing to carry out works through calls for quotations were to apply and be subsequently considered to be included in a contractors’ list, NAO noted that the applications of ten contractors were accepted by the Authority after the expiration of the set deadline for submissions, while a further two were accepted even-though they did not fully meet the requirements set in the application. Furthermore, NAO is also concerned by a number of instances in which it could not find any documented approvals for issuance of calls for quotations.
Notwithstanding these identified concerns, NAO acknowledges the Authority’s challenges while inspecting reported damages as HA Officials can sometimes find themselves taking no more than an educated guess on the extent and nature of works required in view of the ever present possibility of hidden defects. Furthermore, NAO also understands the difficult challenge faced by HA of having to contend with a prevailing perception harboured by a portion of residing tenants of not feeling obliged to carry out any maintenance whatsoever in their housing units. This outlook is often the cause of the occurrence of significant damages to the residential structures due to the lack of simple, regular and largely inexpensive maintenance.
These issues, along with others, are comprehensively addressed in this audit report. A number of recommendations also feature. Report may be accessed through the NAO website: www.nao.gov.mt.