AN ANALYSIS OF WASTESERV MALTA LIMITED’S PROCUREMENT: A CASE STUDY PERSPECTIVE
An essential component in ascertaining value for money is a realistic initial project estimate. In the cases reviewed, NAO noted that there were significant divergences from WSM’s initial estimation of costs to actual contracted amounts. Shortcomings in this regard imply that WSM did not have a reliable benchmark against which to gauge the financial viability of offers received.
NAO considered such substantial differences between WSM estimates and contracted amounts, ranging from 42 per cent over-estimation to 15 per cent under-estimation, attributable to two possible factors. First, such discrepancies may have been indicative of poor estimate compilation, with insufficient attention directed towards the sourcing of essential market intelligence. Second, discrepancies of this magnitude may also have resulted from vast changes to project scope and/or design.
Aside from reservations in determining value for money emerging in relation to the reliability of project estimates, NAO noted significant variations that mainly stemmed from changes in project design after contract award. Variations between contracted amounts and final project costs were most pronounced in two case studies, that is, the construction of a leisure area at the Marsaskala Family Park and the improvement undertaken with respect to the Sant’ Antnin Waste Treatment Plant and Material Recycling Facility. In these two cases, the recorded variations amounted to approximately €600,000 (53 per cent over the contracted amount) and €6,000,000 (23 per cent over the contracted amount), respectively.
Various audit concerns emerged with respect to the other case studies analysed. The Gozo Waste Treatment and Transfer Facility project at Tal-Kus was being reviewed by WSM, with the possibility of major changes in project scope and design. At this early stage, the cumulative value of variations is indicated as 23 per cent of the contract value. The main audit concern of the contract for the supply and maintenance of play equipment at the Marsaskala Family Park was WSM resorting to a negotiated contract, and the fact that this process involved only one contractor. The concern arose from the justification presented, since the nature of the procurement did not warrant the claimed urgency. With reference to the period contracts for the removal and export of filter cake and boiler dust, NAO questioned the resort to such contracts rather than a longer term tender.
Out of the 15 appeals lodged against WSM during the period 2011-2012, 10 of these objections were upheld by PCRB. In NAO’s opinion, this situation left much to be desired, particularly so when one considered the process of review that such procurement is subjected to. It transpired that PCRB overturned the award decisions for a variety of reasons. Most notable were instances where the contract was awarded to a non-compliant bidder, the award of a contact despite ambiguity in tender instructions, a lack of adherence to the stipulated evaluation criteria, and a case where an appellant had to lodge three appeals with respect to the same contract.
The Report may be accessed through the NAO website - www.nao.gov.mt.