ITALIAN UNDER-SECRETARY OF STATE FOR FOREIGN AFFAIRS VISITS IP5 ROAD WORKS
Italian Under-Secretary of State for Foreign Affairs, Sen. Roberto Antonione this afternoon toured the road works being funded under the Fifth Italo-Maltese Financial Protocol. Minister for Urban Development and Roads, Jesmond Mugliett accompanied Senator Antonione during his visit.
The work on Lot 1 includes the complete reconstruction of around 5.5 kilometres of arterial and distributor roads and three major traffic junctions near the Mtarfa Military Cemetery , at Tal-Qlejja and at Tarġa Gap, l/o Mosta.
Senator Antonione and Minister Mugliett toured the works at Triq Buqana and the Tal-Qlejja roundabout junction. The contractor at the site is at present putting the finishing touches to Triq Buqana. This 1.5 kilometre-road will be opened to traffic once the works on the roundabout junctions at both its ends are completed at the end of June.
The reconstruction of Tal-Qlejja roundabout junction was one of the most logistically challenging phases of the Italian Protocol Project due to the large number of services and utilities converging on this roundabout. The roundabout is in fact a hub for three common service ducts which will carry a total of 5 high-tension cables. Seven (7) water mains with a diameter ranging between 100mm to 450mm also meet under this roundabout.
No less than 13.5 kilometres of water mains and 9 kilometres of electricity mains will be laid along the roads that make up Lot 1, once work is completed. The work also involves the installation of 2 kilometres of precast common service ducts and 3.6 kilometres of 6-way duct routes as well as the construction of 5.5 kilometres of storm water systems.
Meanwhile work is progressing steadily on the 1.6-kilometre stretch of road linking Tal-Qlejja with Tarġa Gap. Apart from the reconstruction and realignment of the road, work here involved the laying of pre-cast common service ducts all along under the pavements. This road will be opened to traffic in mid-July.
Of particular interest to this Lot , was the discovery of two cultural assets during the course of the works. The first to be found were a number of underground chambers forming part of the Ta’ Bistra Catacombs complex near Tarġa Gap. A second finding – this time involving part of the Victoria Lines - happened a fortnight ago during excavation works along the road leading from Tal-Qlejja to Żebbiegħ. Further investigations at both sites were carried out under the supervision of an Environmental and Archaeological Monitor and particular measures are being taken to ensure that this archaeological heritage is preserved.
Despite the discovery of the Victoria Lines, the reconstruction of the 2.6 kilometre-road leading from Tal-Qlejja to Żebbiegħ is now two-thirds along its term. Having started in January this year, the works on this road are set to be completed in September as scheduled.
Though the original term of the Fifth Italo-Maltese Protocol has been extended by two years till September 2007, the programme of works on these roads has not changed and the deadline for their completion remains September 2005.
Speaking to the press after the tour, Minister for Urban Development and Roads, Jesmond Mugliett thanked the Italian Government’s assistance on this project.
“This €30 million project will not only leave behind 16 km of roads that offer an excellent driving experience. It leaves behind a legacy of knowledge in road construction brought about by the close collaboration between Maltese and Italian road contractors.”
Minister Mugliett concluded: “I hope that the close relationship that now exists between our two countries in the field of road construction, will continue to bear fruit in the future as Malta continues with its road network upgrade programme by tapping new sources of foreign assistance, particularly European Union funds.”
Work on several road stretches is now nearing completion and delivery. Two stretches of Mdina Road – one 1.4 km long in Qormi and a second 2.2 kilometre-long stretch between Żebbuġ and Rabat , have already been opened to traffic. Other stretches in Qormi, Żebbuġ will be opened to traffic over the coming month.
Stqarrijiet Oħra:
PR261947
STQARRIJA MILL-UFFIĊĊJU TAD-DEPUTAT PRIM MINISTRU U MINISTERU GĦAS-SAĦĦA Ċ...
PR261946