PROJECTS CURRENTLY UNDERWAY AT THE MEDITERRANEAN CONFERENCE CENTRE

PR0831
Date Icon 06/06/2005

Various projects are currently being realised at the Sacra Infermeria of the Mediterranean Conference Centre. 

Since its inception as a conference centre an ongoing restoration and maintenance programme has kept the unique historical character of this national monument, while providing a modern venue able to handle major international conferences, exhibitions, banquets and theatrical events. The MCC, the flagship of conference venues on the Island , is now renowned for its outstanding services and facilities.  

The Centre’s Façade  

The façade of the Mediterranean Conference Centre was a very plain construction with an austere wall, with – originally – a number of windows relatively small, in the upper level of the wall.Later, in 1662, the Main Ward was extended in a westerly direction from its original length of 56.4m to its present dimension of 155m.  During the occupation of the Holy Infirmary by the British Army, several alterations were carried out mainly between 1863 and 1865.  These consisted mainly in the opening of additional windows in the long wall of the Main Ward at ground floor level, the construction of an open stone balcony with a balustrade railing along the facade and the introduction of air inlets and ventilators. 

Under the stewardship of architects from the Ministry for Resources and Infrastructure, responsible for the planning and restoration, the Mediterranean Conference Centre commenced restoration works, in January 2005, on the long façade facing the sea. Permit plans were prepared in order to issue a tender which was eventually awarded to Agius Stoneworks.  Work currently being undertaken includes cleaning, pointing and repair of the existing stonework as well as changing of some stonework when this is deemed necessary.  Cleaning is carried out using dry brushing methods and poulticing.   

Embarking on such a project signified not only improving on the façade’s aesthetics, which has been severely deteriorated along the years, but having the opportunity to preserve a number of interesting features such as mouldings, fascias, lintels of high windows and projections, including  cornices, dormers and ventilators.  

A substantial part of the façade is virtually complete.  Opportunity has been taken to replace windows, which due to sea spray suffered severe damage.  Work on façade windows are being carried out by the MCC’s carpentry department.  A second part is currently being restored by the contractor and works are being carried out without pause in order to meet a deadline set by the Centre for the end of this month.  The final part at the end of the façade together with the main entrance opposite the Evans building are the last two sections which still need to be repaired and restored.  A drastic improvement when compared to the finished sections is immediately observed. 

Complementing the works on the façade, the Centre has also taken the opportunity to completely reconstruct in July the pavement keeping in mind access for all – design guidelines published by the National Commission Persons with Disability.  Concurrently works shall include the lighting of the façade from the pavement and the resurfacing of the street itself.  It is only then that the project may be deemed to be concluded and shall therefore offer the opportunity to conference organisers or other event organisers for their clients to dine or experience an event overlooking the GrandHarbour coupled with a magnificent historical background as the Centre’s façade.   

The La Valette Hall

Phase two of the project, commenced last November, is now complete.   During the transformation of the dilapidated Sacra Infermeria, the La Valette hall had been clad with a 6” leaf wall, possibly erected to cover up in the most economic and fast way, the damage in the walls that had been caused mostly during the British period in Malta, namely holes in the wall to provide a key for partitions.  However this wall which was no more than eight courses high was visually displeasing as its bareness contrasted starkly with the majestic vaulted ceiling.  

Within 22 working days, spread onto two phases due to the Centre’s exigencies, 16 workmen from the Ministry for Resources and Infrastructure, cleaned, pointed, and restored 360m of the original wall which was to be found behind such cladding, the condition of which was totally unknown. The cladding itself was pulled down and taken out by employees from the Mediterranean Conference Centre.  

The third phase of this arduous project is currently underway with the 25 year old air-conditioning system being replaced.  This shall ensure a higher level of service to the Centre’s clients and was designed in a manner so as to avoid inconveniences to the neighbours.  

The final phase of the La Valette Hall’s refurbishment shall commence during the month of June and shall end by the end of August whereby:  

(a)   the Hall’s lighting shall be improved by MCC’s electrical department to meet clients’ requisites and most especially enhance the Hall’s authentic structural design.

(b)   the existing stone wall erected with the kitchen ramp access shall be replaced with a stainless steel railing complemented with tempered glass

(c)    all the 1,500 square metres flooring shall be polished to finally complete all the works in this Hall.  

CHOGM – November 2005

Nothwithstanding these two major projects, other areas are being concurrently upgraded.  Although each of these projects have been planned to be carried out within a span of two years, that is up to 2006, all works have been re-planned to be completed in time for the Commonwealth Heads of Government (CHOGM) Meeting to the held at the Mediterranean Conference Centre next November.  

These include:  

(a)the restoration of both the interior and exterior of the Chapel situated along the ‘Sacra Infermeria’.  When completed this should be a valuable tourist attraction and an alternative venue to accommodate civil marriages.
(b)The refurbishing of the two lifts at the Centre to be in conformity with EU standards and according to the access for all – design guidelines.  Meanwhile, opportunity shall be taken to tastefully refurbish their interior.
(c)Refurbishing of the first floor sanitary facilities
(d)Redecoration of the stalls entrance to Republic Hall
(e)Refurbishing of the back stage sanitary facilities

Meanwhile, all logistical requirements in connection with the various activities for the CHOGM meeting are on track.  

The Minister for Tourism and Culture Francis Zammit Dimech visited the Mediterranean Conference Centre where he was shown round the works being carried out. “Such projects are a testimony to the Centre’s and the Ministry’s intention to further strengthen Malta’s position in the conference and incentive market,” said Minister Francis Zammit Dimech who added that  undoubtedly, the Mediterranean Conference Centre, even through its continuous renovation as experienced today, provides a unique opportunity with a historical character to those conference organisers who want to impress and offer something distinctive about Malta.  

Minister Francis Zammit Dimech said that the Conference and Incentive sector was one of the most import tourism segments for our country. He said that this segment attracts 60,000 annual visitors which together with 27,000 other visitors who come to Malta for business reasons give Malta a 0.4 per cent share of the European outbound business market travelling by air. He said that 76 per cent of these visitors are accomodated in 5 star hotels, 23 per cent in 4 Star hotels with the other one per cent in other serviced accommodation. Minister Zammit Dimech said that total expenditure by this segment amounts to Lm27.3 million of 6 per cent of total tourism expenditure.

Ixxerja din l-istqarrija Icon socials Icon socials Icon socials Icon socials

Stqarrijiet Oħra:

STQARRIJA MILL-UFFIĊĊJU TAD-DEPUTAT PRIM MINISTRU U MINISTERU GĦAS-SAĦĦA  Ċertifikazzjoni internazzjonali tal-ogħla livell għad-dipartiment tar-radjoterapija fiċ-Ċentru tal-Onkoloġija Sir Anthony Mamo

PR261947

STQARRIJA MILL-UFFIĊĊJU TAD-DEPUTAT PRIM MINISTRU U MINISTERU GĦAS-SAĦĦA Ċ...

STQARRIJA MILL-MINISTERU GĦALL-EDUKAZZJONI U L-ISPORT  Aktar minn 1,800 student jiggradwaw mill-Università ta’ Malta

PR261946

STQARRIJA MILL-MINISTERU GĦALL-EDUKAZZJONI U L-ISPORT Aktar minn 1,800 stu...

Aktar Stqarrijiet Right arrow